HomeBlog › Delay Analysis
Delay Analysis

Ramadan and monsoon: how seasonal working hours affect delay calculations

Reduced hours in the Gulf, reduced days in India. Both change how many working days a notice window contains and how much a hindrance actually cost in output. Here is how to model them without overclaiming.

Two predictable seasons change the arithmetic of delay in the regions where FIDIC and NHAI contracts dominate. In the Gulf, Ramadan brings legally reduced working hours for the fasting workforce and, in summer, midday outdoor work bans. In India, the monsoon reduces or halts earthwork and concreting on many highway packages for weeks. Neither is an excusable delay by itself. Both affect the numbers around one.

Three places the season shows up

WhereEffectHow to handle it
Notice deadlines counted in working daysPublic holidays around Eid and reduced-day periods change the countMaintain a per-project holiday list and a defined reduced-working period; compute working days from it, not from a generic calendar
Time impact of a hindranceA 20-day hindrance during monsoon may have displaced less productive time than 20 days in the dry season; conversely, a delay that pushes work from dry season into monsoon multiplies its effectModel the programme with the seasonal calendars it was planned on; a delay analysis that ignores calendars overstates or understates impact
Prolongation costReduced-hour periods have different daily costs; idle plant during a monsoon standstill may already have been plannedSeparate the cost of extended time from the cost of seasonal standstill that would have occurred anyway

The season is usually the contractor's risk

Under most standard forms, ordinary seasonal conditions are foreseeable and priced by the contractor. Only exceptionally adverse weather, measured against records, gives an extension, and it usually gives time without money. The argument is never that the monsoon delayed the works. The argument is that an employer-caused delay pushed critical work into the monsoon, and the programme shows the resulting knock-on. That is a legitimate and often large effect, and it depends entirely on the baseline having been planned with a seasonal calendar the Engineer accepted.

The season is not the delay. The delay is what moved the work into the season.The framing that survives an Engineer's review

Practical modelling

  1. Define the seasonal calendar in the baseline: reduced hours for Ramadan, reduced or non-working days for monsoon, summer midday bans where applicable.
  2. Keep weather records from an objective source, so exceptional weather can be distinguished from ordinary seasonal weather.
  3. Compute notice deadlines from the project's actual calendar, including holidays that move each year.
  4. In the time impact section, show the calendar used and state plainly where a knock-on into the season occurred.

What this means in practice

  • Ordinary seasons are priced risk; the knock-on from an employer delay into a season is claimable.
  • Keep per-project calendars with holidays and reduced-working periods.
  • Use objective weather records to separate exceptional from ordinary.
  • State the calendar assumptions in the claim.

Each DraftMyEOT project carries its own weekend profile, editable holiday list, and user-defined reduced-working periods, so working-day deadlines and delay narratives reflect the real calendar.

Start a 48-hour draft →

This article is general information about how these contract mechanisms typically work. It is not legal advice, and it is not a substitute for review of your specific contract by a qualified professional.