HomeBlog › Contract Defenses
Contract Defenses

Global claims: why Engineers and courts reject them

A global claim asks for a total without linking each cause to each effect. It is the claim you end up with when the register was not kept. Here is what it is, why it fails, and how to avoid writing one.

A global claim, sometimes called a total cost or rolled-up claim, presents the contractor's overall loss or delay and attributes it collectively to a list of events, without showing which event caused which part of the loss. It is the natural product of a project where the records were not kept event by event, and it is disfavoured almost everywhere.

Why it is rejected

A global claim is what the records leave you with when they were not kept per event.Why the fix is upstream

The alternative: per-event narratives

The structure that avoids a global claim is mechanical. One register entry per event, with its own dates, cause, responsible party, and evidence. One paragraph per event in the statement of facts, citing its own records. One time impact per event, with overlaps addressed explicitly. A cost section that allocates line items to periods, not to the project as a whole. Built this way, the claim cannot be global, because each cause is already linked to its effect.

Where a global element is unavoidable

Disruption, as distinct from delay, is the usual case: productivity loss across many small events that cannot each be measured. Even then, the strongest presentations isolate what can be isolated, present the residual disruption separately with a measured-mile or similar analysis, and state candidly why finer separation is impracticable. A tribunal is far more receptive to a small, honest global element than to a large one presented as if it were specific.

What this means in practice

  • One event, one entry, one paragraph, one evidence set.
  • Address overlap and concurrency explicitly.
  • Allocate cost to periods and events, not to the project.
  • If a global element is unavoidable, keep it small, separate, and candid.

DraftMyEOT drafts per-event narratives with inline evidence citations and warns when two open events overlap, so the claim is structured against the global defence from the start.

Start a 48-hour draft →

This article is general information about how these contract mechanisms typically work. It is not legal advice, and it is not a substitute for review of your specific contract by a qualified professional.