What documents do you need for an EOT claim in India

Fourteen categories of record, ordered by how often their absence sinks a claim. Which ones the site must create as they go, and which can be collected later.

The difference between an EOT application that is granted and one that is whittled down is rarely the argument. It is whether the records exist. This list is ordered by how often the absence of each category damages Indian infrastructure claims, in our reading of published arbitration outcomes and practitioner commentary.

Must be created at the time

These cannot be reconstructed. If the site did not make them when the hindrance was live, they do not exist.

#RecordWhat good looks like
1Hindrance registerNumbered entries with occurrence and removal dates, location, responsible agency, letter reference, AE countersignature
2Site diariesDaily, signed, with weather, manpower, plant, and the specific obstruction noted; handwritten is fine if photographed and filed
3Dated photographs and videoOf the obstruction itself: the un-handed-over land, the utility pole, the flooded stretch; with date and chainage
4Notice letters and follow-upsNumbered, dispatched, with proof of delivery; follow-ups on continuing hindrances at a fixed interval
5Programme baseline and monthly updatesSubmitted to the AE at the time, showing progress as it was, so a time impact analysis is possible later
6Manpower and plant deployment recordsDaily returns showing what was idle where, feeding both the delay narrative and the prolongation cost

Should be kept as a matter of routine

#RecordWhy it matters
7Meeting minutesMonthly progress meetings where hindrances were raised; an AE-signed minute is near-countersignature
8RFIs and responsesLate responses are classic hindrances; the RFI log shows the gap
9Drawing register with revision datesProves when a drawing was needed versus when it arrived
10Instructions and variation ordersScope changes that consumed time
11Weather recordsFrom the nearest official station where possible, for monsoon and abnormal weather events

Can be collected later

#RecordNote
12Contract with all Schedules and amendmentsEssential for clause citations; obtainable from the file
13Material delivery recordsSupport disruption and cost heads
14Payment certificates and cost recordsFor the prolongation cost claim, not the time claim
Six of the fourteen cannot be created after the fact. Those six decide most claims.Why the evidence checklist is a site discipline, not a claims-stage exercise

Using the list as a gap check

For each hindrance, mark which of the fourteen categories exist. The gaps in categories 1 to 6 are the ones to task the site with immediately, while the hindrance is still live and the record can still be genuine. Gaps in 7 to 14 can be filled from the office. A claim that goes in with the first six complete and honestly cited is already ahead of most.

What this means in practice

  • Run the gap check per hindrance, not per project.
  • Task the site with categories 1 to 6 while the hindrance is live.
  • Number every record so the annexure list writes itself.
  • Keep cost records separate; they support a different claim.

Every delay event in DraftMyEOT shows a gap checklist across the evidence categories, filling in as records are linked, so the site can be tasked while the record can still be created.

Start a 48-hour draft →

This article is general information about how these contract mechanisms typically work. It is not legal advice, and it is not a substitute for review of your specific contract by a qualified professional.