HomeBlog › Time-Bars
Time-Bars

Back-to-back subcontracts: how to protect your EOT rights as a subcontractor

Your subcontract mirrors the main contract's time-bars downward, usually with a shorter window so the main contractor can pass your notice up. One event, two clocks, and the second one is yours to lose.

A back-to-back subcontract passes the main contract's terms down to the subcontractor, including its notice requirements and time-bars. In the Gulf and on Indian packages it typically shortens them: if the main contractor has 28 days to notify the Employer, the subcontractor may have 14 or 21 to notify the main contractor, so there is time to pass the claim up the chain. The subcontractor's entitlement depends on hitting the shorter window.

One event, two clocks

ClockRuns betweenTypical windowWhat is at stake
UpstreamMain contractor and Employer28 days from awareness under FIDIC, or as amendedThe main contractor's entitlement, which your relief usually depends on
DownstreamYou and the main contractorShorter, often 14 or 21 days, from your awarenessYour own right to time and cost under the subcontract

If you notify late, two things happen. Your own claim against the main contractor is time-barred under the subcontract. And the main contractor may argue that your lateness prevented it from notifying the Employer in time, leaving you exposed to its loss as well. The downstream clock protects you from both.

Pay-when-certified and pay-if-paid traps

Many back-to-back forms make the subcontractor's EOT and cost recovery conditional on the main contractor obtaining relief from the Employer. Where that is the case, your interest in the upstream claim is direct. Ask to see the notice the main contractor gave, and keep a copy against your register entry. If the main contractor never notified the Employer, your subcontract may give you a separate route, or it may not; that is a question for your contracts lead, and the answer depends on the wording.

Your notice is the main contractor's evidence. Send it early enough to be useful to them, not just in time to be valid for you.Why the downstream window is short

Practical protection

  1. Read the subcontract's notice clause separately from the main contract's. The window, trigger, and form are often different.
  2. Track both clocks for every event. Your deadline and the main contractor's. When yours is met, ask for confirmation that theirs was.
  3. Keep your own records. Do not rely on the main contractor's site diary or programme. Your evidence locker is yours.
  4. Notify the main contractor even for its own delays. A main-contractor-caused delay is still an event under your subcontract, with its own window.
  5. Preserve rights on continuing delays. Periodic follow-up notices, downstream and, where you can see it, upstream.

What this means in practice

  • Two clocks per event; the shorter one is yours.
  • Confirm the upstream notice was given; your relief may depend on it.
  • Keep independent records.
  • Main-contractor delay is notifiable too.

A back-to-back profile in DraftMyEOT spawns two linked clocks for each event: the upstream deadline and the downstream deadline that preserves your own rights.

Start a 48-hour draft →

This article is general information about how these contract mechanisms typically work. It is not legal advice, and it is not a substitute for review of your specific contract by a qualified professional.