The 14-category evidence checklist for a winning EOT claim

What a complete claim file contains, category by category, with the question to ask about each. Print it, pin it in the site office, and run it per event.

A complete delay claim file has fourteen kinds of record in it. Most claims go in with six or seven. The list below is the checklist we use inside the product, and the question beside each category is the one an Engineer or tribunal will ask.

#CategoryThe question it answers
1Contract with all Particular Conditions and amendmentsWhat exactly did the parties agree, including the changes to the standard form?
2Letters and transmittalsWhat was said, to whom, and when?
3Site diariesWhat happened on site each day, recorded that day?
4Dated photographs and videoCan the obstruction be seen?
5Meeting minutesWas the delay raised and acknowledged at the time?
6RFIs and responsesWhen was information needed, and when did it arrive?
7Baseline programme and every updateWhat was the plan, and what was the actual progress at the time of the event?
8Manpower and plant deployment recordsWhat resources were idle or diverted, and when?
9Material delivery recordsWere materials held, diverted, or wasted?
10Weather recordsWas the weather abnormal, by an objective measure?
11Drawing register with revision datesWhen was each drawing issued and revised?
12Instructions and variation ordersWhat scope changed, and when was it instructed?
13Payment certificates and cost recordsWhat did the extended period actually cost?
14The notice logWhich notices were given, when, and by what method?

How to use it

Run the list per delay event, not per project. A project-level file can look complete while a specific event has no photograph, no diary entry, and no notice. For each event, mark each category as present, missing, or not applicable. The missing ones in categories 3, 4, 5, 7, 8, and 14 are the urgent ones: they can only be created contemporaneously.

Records created at the time beat memories reconstructed later, every single time.Rule one of delay claims

The three categories teams most often skip

What this means in practice

  • Gap-check per event, not per project.
  • Six categories are contemporaneous only; task the site with them while the event is live.
  • Archive programme updates as submitted.
  • Keep a real notice log.

DraftMyEOT shows this checklist on every delay event, filling in as evidence is linked, and the claim draft's annexure list is built from the same references.

Start a 48-hour draft →

This article is general information about how these contract mechanisms typically work. It is not legal advice, and it is not a substitute for review of your specific contract by a qualified professional.